Contract No:  NE/2017/03

 

DEVELOPMENT OF

ANDERSON ROAD QUARRY SITE -

ROAD IMPROVEMENT WORKS
 

 

Baseline monitoring Report

                                      

 
 

 

 

 

 

 

CLIENTS:

PREPARED BY:

 

Civil Engineering and Development Department

 

 

Lam Environmental Services Limited

 

11/F Centre Point

181-185 Gloucester Road

Wanchai, H.K.

 

Telephone: (852) 2882-3939

Facsimile: (852) 2882-3331

E-mail: info@lamenviro.com

Website: http://www.lamenviro.com

 

 

 

 

 

CERTIFIED by:



 

 

 

 

Derek LO

Environmental Team Leader

 

 

 

DATE:

17 December 2018

 

 

 


Table of Contents

 

Executive Summary. 4

 

1 Introduction.. 8

1.1 Background. 8

1.2 Purpose of Baseline Monitoring Report 9

 

2 Air Quality Monitoring.. 10

2.1 Monitoring Requirements. 10

2.2 Monitoring Equipment 10

2.3 Monitoring Locations. 11

2.4 Monitoring Parameters, Frequency and Duration.. 11

2.5 Monitoring Methodology. 12

2.6 Results and Observations. 13

2.7 Action and Limit Levels. 13

 

3 NOISE MONITORING.. 15

3.1 Monitoring Requirements. 15

3.2 Monitoring Equipment 15

3.3 Monitoring Locations. 16

3.4 Monitoring Parameters, Frequency and Duration.. 16

3.5 Monitoring Methodology. 17

3.6 Results and Observations. 17

3.7 Action and Limit Levels. 18

 

4 WATER QUALITY MONITORING.. 19

4.1 Monitoring Requirements. 19

4.2 Monitoring Equipment 19

4.3 Monitoring Locations. 20

4.4 Monitoring Parameters, Frequency and Duration.. 20

4.5 Monitoring Methodology. 20

4.6 Results and Observations. 21

4.7 Action and Limit Levels. 22

 

5 Revision for inclusion into EM&A Manual 26

 

6 Comment and Conclusions. 27

 

 

 

 

 

 

 

 

 

 

 

 

LIST OF FIGURES

Figure 1.1 Project Layout

Figure 2.1 & 2.2 Location of Baseline Air Quality Monitoring Stations

Figure 3.1 & 3.2 Location of Baseline Noise Monitoring Stations

Figure 4.1 & 4.2 Location of Baseline Water Quality Monitoring Stations

 

 

 

LIST OF APPENDIXES

Appendix A Baseline Monitoring Schedule for Air Quality, Noise and Water Quality Monitoring

Appendix B Calibration Certificates of the Monitoring Equipment

Appendix C Baseline Air Quality Monitoring Data

Appendix D Wind Data

Appendix E Baseline Noise Monitoring Data

Appendix F Baseline Water Quality Monitoring Data


Executive Summary

i.             This is the Baseline Monitoring Report to report the baseline monitoring findings for the Project of Development of Anderson Road Quarry Site -Road Improvement Works.

ii.            During the baseline monitoring, the baseline air quality and noise monitoring were conducted at EIGHT designated air quality monitoring stations and FIVE designated noise monitoring stations for consecutive 14 days in accordance with the EM&A Manual. The baseline water monitoring shall be carried out at FOUR designated monitoring stations, three days per week, for at least 4 weeks prior to the commencement of construction works.

iii.           Due to adverse weather condition, the baseline air and noise monitoring on certain days were rescheduled.

iv.           This report presents the baseline air quality and noise monitoring findings and information record during the period from 13 August 2018 to 29 August 2018 and 13 August 2018 to 2 September 2018 respectively, while that for the baseline water quality monitoring were recorded during the period from 13 August 2018 to 7 September 2018. No construction activities under the Project were undertaken during the baseline monitoring period.

 

Air Quality Monitoring

v.            Air quality monitoring was conducted and recorded in terms of 1-hour Total Suspended Particulates (TSP). The average 1-hour TSP levels established at the EIGHT air quality monitoring stations are summarized as shown in Table I. The average results and Action & Limit levels of baseline 1-hour TSP levels are summarized as shown in Table II.

 

Table I Summary of Averaged 1-hour TSP Levels

Monitoring Station ID

Monitoring Station

1-hour TSP Level in µg˘Am3

Average (µg˘Am3)

Range (µg˘Am3)

NCWBR_AMS-1

Shun Lee Fire Station

52.9

13.4 - 127.2

NCWBR_AMS-2

Shun Lee Estate Lee Hang House

49.8

14.8 - 106.3

NCWBR_AMS-3

Shun Lee Disciplined Services Quarters (Block 6)

58.3

6.3 - 126.1

NCWBR_AMS-4

Sienna Garden

48.6

10.6 - 99.3

NCWBR_AMS-5

Shun Chi Court Shun Fung House

30.8

2.6 - 76.0

LTR_AMS-1

St Edward's Catholic Primary School

34.0

7.8 - 113.6

LTR_AMS-2

Environmental Protection Department's Restored Landfill Site Office

47.8

4.8 - 110.7

LTR_AMS-3

Po Tat Estate Tat Kai House

54.0

11.9 - 138.2

 

 

 

 

Table II Summary of Averaged Results and Action & Limit Levels of Baseline 1-hour TSP Levels

Monitoring Station

1-hour TSP Level in µg˘Am3

Action Level (µg˘Am3)

Limit Level (µg˘Am3)

Average

Range

NCWBR_AMS-1

52.9

13.4 - 127.2

284.4

500.0

NCWBR_AMS-2

49.8

14.8 - 106.3

282.4

500.0

NCWBR_AMS-3

58.3

6.3 - 126.1

287.9

500.0

NCWBR_AMS-4

48.6

10.6 - 99.3

281.6

500.0

NCWBR_AMS-5

30.8

2.6 - 76.0

270.0

500.0

LTR_AMS-1

34.0

7.8 - 113.6

272.1

500.0

LTR_AMS-2

47.8

4.8 - 110.7

281.1

500.0

LTR_AMS-3

54.0

11.9 - 138.2

285.1

500.0

 

Noise Monitoring

vi.           The baseline noise levels established at FIVE monitoring stations are summarized as shown in Table III. The averaged results and Action & Limit levels of baseline noise levels are summarized as shown in Table IV to VI.

 

Table III Summary of Averaged Baseline Noise Levels

Monitoring Station

0700-1900 hrs on normal weekdays

0700-2300 hrs on holidays (including Sundays); and 1900-2300 hrs on all days

2300-0700 hrs of all days

Leq (30min), dB(A)

Leq (5min), dB(A)

Average

Range

Average

Range

Average

Range

NMC01

69.3

67.8 - 70.5

69.0

61.2 - 71.8

66.6

60.6 - 71.6

NMC02

72.0

70.3 - 73.1

66.3

63.3 - 69.6

68.6

62.4 - 71.9

NMC03

78.2

77.1 - 79.5

77.9

73.3 - 82.1

73.8

65.8 - 79.7

NMC04

66.6

63.7 - 70.3

64.0

61.9 - 71.8

62.1

58.7 - 66.0

NMC05

61.8

59.2 - 64.8

59.8

56.5 - 73.7

57.9

53.6 - 62.0

Remark: Each of the daily 30 minutes sampling period include six consecutive Leq (5min) reading

 

 

 

 

 

 

Table IV Summary of Results and Action & Limit Levels of Baseline Noise Levels (0700-1900 hrs on normal week days)

Monitoring Station

Time Period

Parameter

Average

Range

Action Level

Limit Level

dB(A)

NMC01

0700-1900 hrs on normal weekdays

Leq, 30min

69.3

67.8 - 70.5

When one documented complaint is received

65 / 70

NMC02

72.0

70.3 - 73.1

75

NMC03

78.2

77.1 - 79.5

75

NMC04

66.6

63.7 - 70.3

75

NMC05

61.8

59.2 - 64.8

75

Remark: Limit level of NMC01 reduce to 65 dB (A) during examination periods if any.

 

Table V Summary of Results and Action & Limit Levels of Baseline Noise Levels (0700-2300 hrs on holidays (including Sundays); and 1900-2300 hrs on all days)

Monitoring Station

Time Period

Parameter

Average

Range

Action Level

Limit Level

dB(A)

NMC01

0700-2300 hrs on holidays (including Sundays); and 1900-2300 hrs on all days

Leq, 5min

69.0

61.2 - 71.8

When one documented complaint is received

60 / 65 / 70 *

NMC02

66.3

63.3 - 69.6

NMC03

77.9

73.3 - 82.1

NMC04

64.0

61.9 - 71.8

NMC05

59.8

56.5 - 73.7

Remark: Construction noise during restricted hours is under the control of Noise Control Ordinance and Limit Level to be selected based on Area Sensitivity Rating

* Limit Level for restricted hour monitoring shall act as reference level only. Investigation would be conducted on CNP compliance if exceedance recorded during restricted hour noise monitoring period.

 

Table VI Summary of Results and Action & Limit Levels of Baseline Noise Levels (2300-0700 hrs of all days)

Monitoring Station

Time Period

Parameter

Average

Range

Action Level

Limit Level

dB(A)

NMC01

2300-0700 hrs of all days

Leq, 5min

66.6

60.6 - 71.6

When one documented complaint is received

45 / 50 / 55 *

NMC02

68.6

62.4 - 71.9

NMC03

73.8

65.8 - 79.7

NMC04

62.1

58.7 - 66.0

NMC05

57.9

53.6 - 62.0

Remark: Construction noise during restricted hours is under the control of Noise Control Ordinance and Limit Level to be selected based on Area Sensitivity Rating

* Limit Level for restricted hour monitoring shall act as reference level only. Investigation would be conducted on CNP compliance if exceedance recorded during restricted hour noise monitoring period.

Water Quality Monitoring

vii.         The averaged results and Action & Limit levels of baseline water quality level at FOUR stations are summarized as shown in Table VII and Table VIII.

 

Table VII Summary of Average Results of Baseline Water Quality

Monitoring Station

pH

DO (mg/L)

Turbidity (NTU)

SS (mg/L)

Average

Range

Average

Range

Average

Range

Average

Range

E

7.30

6.59 ˇV 7.95

6.48

6.02 ˇV 6.83

24.73

7.92 ˇV 129.90

22.55

3.25 ˇV 175.80

F

6.94

6.28 ˇV 8.38

6.44

5.40 ˇV 6.82

16.46

5.46 ˇV 78.54

9.69

1.80 ˇV 50.95

H

7.48

6.57 ˇV 8.51

6.23

4.83 ˇV 7.10

184.92

7.62 ˇV 648.48

589.76

2.95 ˇV 5650.25

I

7.38

6.69 ˇV 8.43

6.20

5.42 ˇV 6.72

132.79

7.69 ˇV 894.00

102.28

2.15 ˇV 748.50

 

*Remarks: The value of <1.0mg/L represents the recorded suspended solid level is under the minimum laboratory reporting limit of 1.0mg/L.

 

Table VIII Summary of Action & Limit Level of Baseline Water Quality

Monitoring Station

Surface pH

Surface DO (mg/L)

Surface Turbidity (NTU)

Surface SS (mg/L)

Action Level

Limit Level

Action Level

Limit Level

Action Level

Limit Level

Action Level

Limit Level

E

-

-

-

-

-

-

-

-

F

6.6-8.4

6.5-8.5

5.8

5.5

24.4

32.7

17.0

23.8

H

-

-

-

-

-

-

-

-

I

6.6-8.4

6.5-8.5

5.5

5.4

206.9

214.2

172.8

201.4

 

*Remarks:

The value of 1.0mg/L was taken as the value for measurement with suspended solid level of <1.0mg/L for Action and Limit level calculation.

It is recommended that upstream monitoring station (monitoring station E and H) would be taken as control reference for exceedance investigation only. Action and limit level would not be establish using the baseline data.


1              Introduction

 

1.1          Background

1.1.1.     Development of Anderson Road Quarry Site (ARQ) project is to provide land and the associated infrastructures for the proposed land uses at the existing Anderson Road Quarry Site at the North-eastern of East Kowloon according to the final Recommended Outline Development Plan. ARQ project involved three major infrastructures work contracts namely Contract 1, 2 and 3.

1.1.2.     The scope of works under Contract 3 - Road Improvement Works and Pedestrian Connectivity Facilitates Work Phase 2A (Contract No. NE/2017/03) comprises as below and the location of the Project is shown Figure 1.1.

(i)             Road Improvement Works (RIW) -

a)     RIW 1- at junction of New Clear Water Bay Road and Shun Lee Tsuen Road including the road widening works at New Clear Water Bay Road, modification of existing subway structure and provision of noise mitigation measures;

b)    RIW 2- at junction of Clear Water Bay Road and On Sau Road, including the provision of U-turn facility and noise mitigation measures; and

c)     RIW 3- at junction of Sau Mau Ping Road and Lin Tak Road, construction of bridge above Tseung Kwan O Road, provision of loading and unloading bays along Lin Tak Road and noise mitigation measures.

(ii)            Construction of elevated walkways, escalators and lift towers with associated staircases and lifts for pedestrian connectivity facilities;

(iii)           Bus-bus interchange public toilet;

(iv)          Associated landscaping works, and

(v)           Provision of Barrier-Free Access Facilities at Subway KS27.

1.1.3.     In accordance with Clause 3.3 stated in the Environmental Permit (no.: EP-513/2016), Four hard copy and one electronic copy of the Baseline Monitoring Report shall be submitted to the Director at least 2 weeks before the commencement of construction of the project.

1.1.4.     In accordance with Section 11.2.1 of the Project Environmental Monitoring and Audit (EM&A) Manual, the Baseline Environmental Monitoring Report should be prepared and submitted within 10 working days after completion of the baseline monitoring works.

 

 

 

 

1.2          Purpose of Baseline Monitoring Report

1.2.1.     The purpose of the baseline monitoring is to review the baseline conditions of air quality, noise level and water quality along the Project boundary, and to establish baseline levels for air quality, noise and water quality in accordance with the EM&A Manual. These levels would be used as the basis for assessing environmental impact and compliance during construction stage of the corresponding component the Project

1.2.2.     This baseline monitoring report presents the baseline monitoring requirements, methodologies, monitoring results and determination of the action and limit levels for each monitoring parameter at EIGHT designated air quality monitoring stations, FIVE designated noise monitoring stations and FOUR designated water quality monitoring stations as described in the EM&A Manual.


2              Air Quality Monitoring

 

2.1          Monitoring Requirements

2.1.1       In accordance with the Project EM&A Manual, baseline 1-hour TSP levels at EIGHT air quality monitoring stations should be established by conducting baseline 1-hour TSP monitoring for at least consecutive 14 days prior to the commencement of the construction work. The 1-hour TSP sampling shall be done at least three times per day at each monitoring station.

2.1.2       The baseline air quality monitoring at EIGHT monitoring stations were conducted during the baseline monitoring period from 13 August 2018 to 29 August 2018 and the relevant findings are summarized in this report. The baseline monitoring schedule is shown in Appendix A.

2.1.3       Due to hoisting of typhoon signal No. 3, the baseline air quality monitoring on 14 August 2018 was rescheduled to 27 August 2018.

2.1.4       Due to EPD security concern and unable to access the monitoring station LTR_AMS-2 (EPD Landfill Site Office) on Public Holiday. The baseline air quality monitoring at LTR_AMS-2 on 19 and 26 August 2018 was rescheduled to 28 and 29 August 2018 respectively.

2.1.5       The baseline air quality monitoring of these days were rescheduled until having 14 days baseline monitoring data.

 

2.2          Monitoring Equipment

2.2.1       The 1-hour TSP air quality monitoring was performed by using portable direct reading dust meters at each designated monitoring station. The brand and model of the equipment are given in Table 2.1.

Table 2.1 Air Quality Monitoring Equipment

Equipment

Brand and model

Series Number

Portable direct reading dust meter

Met One BT- 645

R22586

X19295

X19296

X19297

X19298

X19299

Met One AEROCET 831

W14016

W15448

W15449

W16848

Remark: Portable direct reading dust meter Met One 831 W15449 started to use on 20 August 2018.

2.2.2       The calibration certificate and certificate of comparison check with High Volume Sampler of the air quality monitoring equipment listed in Table 2.1 can refer to Appendix B.

 

 

2.3          Monitoring Locations

2.3.1       Given some of the original proposed air quality monitoring locations were either rejected or not favourable for monitoring, fine adjusted monitoring location was therefore proposed (which is (a) at the site boundary or such locations close to the major dust emission source; (b) close to the sensitive receptors; and (c) take into account the prevailing meteorological conditions) based on the procedure under S1.5 of Appendix D2 of the General Technical Requirements of Environmental Monitoring. The detail and information of the monitoring stations for baseline air quality monitoring conducted are presented in Table 2.2 and shown in Figures 2.1 and 2.2.  

 

Table 2.2 Baseline Air Quality Monitoring Stations Location

Monitoring Station ID

Monitoring Location

Level

(in terms of

no. of floor)

NCWBR_AMS-1 1

Shun Lee Fire Station

2/F Roof

NCWBR_AMS-2 2

Shun Lee Estate Lee Hang House

G/F

NCWBR_AMS-3 3

Shun Lee Disciplined Services Quarters (Block 6)

4/F podium

NCWBR_AMS-4 4

Sienna Garden

G/F

NCWBR_AMS-5 5

Shun Chi Court Shun Fung House

Roof

LTR_AMS-1 6

St Edward's Catholic Primary School

G/F

LTR_AMS-2

Environmental Protection Department's Restored Landfill Site Office

G/F

LTR_AMS-3

Po Tat Estate Tat Kai House

3/F podium

Remarks 1: NCWBR_AMS-1 recommended under EM&A manual is surrounded by boundary wall and occupied by planter and emergency vehicle parking area inside the Fire Station which is considered as not representative / suitable for air quality monitoring and not feasible for installation of monitoring equipment. A fine adjusted monitoring location was therefore proposed, where is at the roof of the Fire Station.

 

Remarks 2: As advised by the management office of Shun Lee Estate Lee Hang House, the permission of access could not be obtained from designated monitoring locations proposed in the EM&A manual, a fine adjustment of location at the boundary of Shun Lee Estate Lee Hang House was therefore proposed.

 

Remarks 3: The management office of Shun Lee Disciplined Services Quarters prefers conducting the monitoring at the podium level at 4/F facing New Clear Water Road, where can minimize the disturbance to the residents. A fine adjustment of location was therefore proposed for baseline monitoring.

 

Remarks 4: The recommended monitoring location NCWBR_AMS-4 under EM&A manual is behind the boundary and fence wall which is considered as not representative / suitable for air quality monitoring for the upper floors of the Sienna Garden. A fine adjustment of monitoring location was therefore proposed to represent Sienna Garden.

 

Remarks 5: The recommended monitoring location NCWBR_AMS-5 under EM&A manual is located at the edge of roof top without proper fencing and protection. Due to the safety concern on working at height, a fine adjustment of location was therefore proposed.

 

Remarks 6: As permission of access could not be obtained from St. Edward's Catholic Primary School for conducting monitoring at the recommended monitoring location under EM&A manual, a fine adjustment of location at the boundary of St. Edward's Catholic Primary School was therefore proposed.

 

 

 

 

 

2.4          Monitoring Parameters, Frequency and Duration

2.4.1       The monitoring parameters, frequency and duration of air quality monitoring are summarized in Table 2.3

Table 2.3 Air Quality Monitoring Parameters, Frequency and Duration

Monitoring Period

Duration

Sampling Parameter

Frequency

Baseline Monitoring

At least 14 consecutive days prior to the commissioning of the construction works

1-hour TSP

3 times per day

 

2.5          Monitoring Methodology

2.5.1      Measuring Procedures

(a)           Check the calibration period of portable direct reading dust meter prior to monitoring (The direct reading dust meter was calibrated at 2-years interval and checked with High Volume Sampler (HVS) yearly, details refer to Section 2.5.2)

(b)           Record the site condition near / around the monitoring stations.

(c)           Install the portable direct reading dust meter to the monitoring location.

(d)           Slide the power switch to turn the power on.

(e)           Check of portable direct reading dust meter to ensure the equipment operation in normal condition.

(f)            Select the period of measurement to 60mins.

(g)           Check and set the correct time.

(h)           Select the appropriate unit display for the equipment.

(i)             Slide the power switch to turn the power off when the monitoring period ended (3 times 1 hour TSP monitoring per day).

(j)             Uninstall the portable direct reading dust meter

(k)           Collected the sampled data for analysis.

(l)             Remark: Procedures (c) to (h) may be different subject to the brands and models of portable direct reading dust meter

2.5.2       Maintenance and Calibration

(a)           The direct reading dust meter was calibrated at 2-years interval and checked with High Volume Sampler (HVS) yearly to determine the accuracy and validity of the results measured.

(b)           Checking of direct reading dust meter will be carried out in order to determine the conversion factor between the direct reading dust meter and the standard equipment, HVS. The comparison check is to be considered valid based on correlation coefficient checked by HOKLAS laboratory

 

2.5.3       Wind data

Hong Kong Observatory (HKO) meteorological information is widely accepted to be used in various environmental monitoring practices within HKSAR due to its professional quality and precision. Therefore, the daily wind data including Prevailing Wind Direction (degrees) and Mean Wind Speed (km/h) were obtained from HKO Automatic Weather Station to serve as the representative data for meteorological condition during monitoring, given the overall Project location is divided into three separate works section and the air quality monitoring stations are located at different elevated ground. The representative wind data from Tateˇ¦s Cairn HKO Automatic Weather Station and Tseung Kwan O HKO Automatic Weather Station were obtained covering the 1-hr TSP monitoring periods. The wind data were extracted and shown in Appendix D.

2.6          Results and Observations

2.6.1       The baseline 1-hour TSP monitoring were carried out from 13 August 2018 to 29 August 2018 for consecutive 14 days and the weather were mostly sunny with traces of rainfall. Major dust sources were from nearby traffic emissions.

2.6.2       The baseline monitoring results for 1-hour TSP are summarized in Table 2.4 respectively. Detailed air quality monitoring results are presented in Appendix C.

Table 2.4 Summary of 1-hour TSP Baseline Monitoring Results

Parameter

Monitoring Location

Average (µg˘Am3)

Range (µg˘Am3)

1-hour TSP Level in µg˘Am3

NCWBR_AMS-1

52.9

13.4 - 127.2

NCWBR_AMS-2

49.8

14.8 - 106.3

NCWBR_AMS-3

58.3

6.3 - 126.1

NCWBR_AMS-4

48.6

10.6 - 99.3

NCWBR_AMS-5

30.8

2.6 - 76.0

LTR_AMS-1

34.0

7.8 - 113.6

LTR_AMS-2

47.8

4.8 - 110.7

LTR_AMS-3

54.0

11.9 - 138.2

2.7          Action and Limit Levels

2.7.1       The Action and Limit Levels for air quality impact monitoring were based on the criteria adopted from the EM&A Manual as presented in Table 2.5.

 

Table 2.5 Derivation of Action and Limit Levels for Air Quality

Parameters

Action Level

Limit Level

1-hour TSP

Level in Łgg/m3

For baseline level 384Łgg/m3, Action level =

(baseline level * 1.3 + Limit level)/2;

For baseline level > 384Łgg/m3, Action level = Limit level

500 Łgg/m3

 

2.7.2       The derived Action and Limit levels are presented in Table 2.6.

 

Table 2.6 Derived Action and Limit Levels for Air Quality

Parameter

Monitoring Station

Action Level (µg˘Am3)

Limit Level (µg˘Am3)

1-hour TSP

 Level in µg˘Am3

NCWBR_AMS-1

284.4

500.0

NCWBR_AMS-2

282.4

500.0

NCWBR_AMS-3

287.9

500.0

NCWBR_AMS-4

281.6

500.0

NCWBR_AMS-5

270.0

500.0

LTR_AMS-1

272.1

500.0

LTR_AMS-2

281.1

500.0

LTR_AMS-3

285.1

500.0

3              NOISE MONITORING

3.1          Monitoring Requirements

3.1.1       In accordance with the EM&A Manual, the baseline noise monitoring at FIVE monitoring stations shall be carried out daily for a period of at least two weeks

3.1.2       The baseline noise monitoring at FIVE monitoring stations were conducted during the monitoring period from 13 August 2018 to 2 September 2018 and the relevant findings are summarized in this report. The baseline monitoring schedule is shown in Appendix A.

3.1.3       Due to hoisting of typhoon signal No. 3, the baseline noise monitoring on 14 August 2018 (all time period) was rescheduled to 27 August 2018. The baseline noise monitoring on 27 August 2018 (1900-2300 hours and 2300-0700 hours of next day) was further rescheduled to 30 August 2018 due to the adverse weather condition.

3.1.4       Due to adverse weather condition, the baseline noise monitoring on 22 August 2018 from 1900-2300 hours was rescheduled to 28 August 2018. The baseline noise monitoring on 28 August 2018 was further rescheduled to 31 August 2018 due to the adverse weather condition.

3.1.5       Due to adverse weather condition, the baseline noise monitoring at NMC04 and NMC05 on 23 August 2018 from 1900-2300 hours was rescheduled to 29 August 2018. The baseline noise monitoring at NMC04 and NMC05 on 29 August 2018 from 1900-2300 hours was further rescheduled to 1 September 2018 due to the adverse weather condition.

3.1.6       Due to adverse weather condition, the baseline noise monitoring on 26 August 2018 (2300-0700 hours of next day) was rescheduled to 1 September 2018.

 

3.2          Monitoring Equipment

3.2.1      Noise monitoring was performed using sound level meter at the designated monitoring locations. The sound level meters shall comply with the International Electrotechnical Commission Publications 651:1979 (Type 1) and 804:1985 (Type 1) specifications. Acoustic calibrator shall be deployed to check the sound level meters at a known sound pressure level. Brand and model of the equipment is given in Table 3.1.

 

Table 3.1 Noise Monitoring Equipment

Equipment

Brand and Model

Series Number

Integrated Sound Level Meter

Larson Davis LxT

0003737

0004796

B&K2238

2160277

HONGLIM HLES-01

201692136

Acoustic Calibrator

Rion NC-73

10707358

Acoustic Calibrator

Larson Davis CAL200

13098

13128

13437

 

3.2.2      The calibration certificates of the noise monitoring equipment are attached in Appendix B.

 

 

3.3          Monitoring Locations

 

3.3.1      Given some of the original proposed noise monitoring locations were not favourable for monitoring, fine adjusted monitoring location was therefore proposed (which is still within the boundary of the designated noise sensitive receivers). In accordance with the EM&A Manual, the noise monitoring stations for baseline noise monitoring is presented in Table 3.2 and shown in Figures 3.1 and 3.2.

 

Table 3.2 Baseline Noise Monitoring Stations

 

Monitoring Station ID

Monitoring Location

Measurement Type

Level

(in terms of no. of floor)

NMC01 1

Kei Shun Special School

Facade

G/F

NMC02

Shun Lee Disciplined Services Quarters Block 6

Facade

3/F podium

NMC03 2

Sienna Garden Block 6

Free-field

G/F

NMC04 3

Po Tat Estate Tat Kai House

Free-field

3/F podium

NMC05

Hong Wah Court Block B Yee Hong House

Facade

G/F

 

Remarks 1: The recommended monitoring location NMC01 under EM&A manual would not be accessible for baseline noise monitoring from 1900 to 0700 hours of next day. The fine adjusted location located between the recommended monitoring location and proposed construction site was proposed, which is accessible from 1900 to 0700 hours of next day.

 

Remarks 2: The recommended monitoring location NMC03 under EM&A manual is behind the boundary and fence wall which is considered as not representative / suitable for noise quality monitoring for the upper floors of the Sienna Garden. A fine adjustment of monitoring location was therefore proposed to represent the boundary condition of Sienna Garden.

 

Remarks 3: The recommended monitoring location NMC04 under EM&A manual is located at semi-enclosed/enclosed area. As such, it was considered as not suitable for noise monitoring. A fine adjustment of monitoring location was therefore proposed at the open area of 3/F Podium of Po Tat Estate Tat Kai House for baseline monitoring.

 

3.4          Monitoring Parameters, Frequency and Duration

 

3.4.1      The monitoring parameters, frequency and duration of noise monitoring are summarized in Table 3.3.

 

Table 3.3 Baseline Noise Monitoring Parameters, Frequency and Duration

Monitoring

Period

Duration

Measurement Parameter

Measurement Period

Frequency

Baseline Monitoring

Consecutive days of at least 2 weeks before commencement of major construction works

A-weighted levels Leq, L10 and L90

Including 30 minutes (six consecutive Leq(5min) readings) for (i), (ii) and (iii)

(i) between 0700 and 1900 hours;

(ii) between 1900 and 2300 hours; and

(iii) between 2300 to 0700 hours of next day

Daily

 

 

3.5          Monitoring Methodology

 

3.5.1      Monitoring Procedure

 

(a)           The monitoring station shall normally be at a point 1m from the exterior of the sensitive receiverˇ¦s building façade and be at a position 1.2m above the ground.

(b)           Facade measurements were made at the monitoring locations. For free-field measurement, a correction factor of +3 dB (A) would be applied.

(c)           The battery condition was checked to ensure the correct functioning of the meter.

(d)           Parameters such as frequency weighting, the time weighting and the measurement time were set as follows:

(i)       Frequency weighting: A time weighting: Fast

(ii)      Time measurement: Daily measurement of A-weighted levels Leq, L10 and L90 shall be conducted for at least two weeks. Daily measurement periods should include: (i) between 0700 and 1900 hours; (ii) between 1900 and 2300 hours; and (iii) between 2300 to 0700 hours of next day. Each of the daily sampling periods shall include 30 minutes (six consecutive Leq(5min) readings).

(e)           Prior and after to the noise measurement, the meter was checked using the acoustic calibrator for 94dB (A) at 1000 Hz. If the difference in the calibration level before and after measurement was more than ˇÓ1 dB (A), the measurement would be considered invalid and repeat of noise measurement would be required after re-calibration or repair of the equipment.

 

3.5.2      Maintenance and Calibration

 

(a)              The microphone head of the sound level meter was cleaned with soft cloth at regular intervals.

(b)              The sound level meter and calibrator were calibrated at yearly intervals.

 

3.6          Results and Observations

3.6.1       The baseline noise monitoring were carried out from 13 August 2018 to 2 September 2018 for recording over two weeks monitoring data and the weather were mostly sunny with traces of rainfall. During the baseline monitoring period, no construction activities were observed. The major noise source was traffic noise around the monitoring stations (especially Clear Water Bay Road near NMC03).

 

3.6.2       The baseline noise monitoring results are summarized in Table 3.4 respectively. Detailed noise monitoring results are presented in Appendix E.

 

 

 

 

 

 

 

Table 3.4 Summary of Baseline Noise Monitoring Results

Monitoring Station

0700-1900 hrs on normal weekdays

0700-2300 hrs on holidays (including Sundays); and 1900-2300 hrs on all days

2300-0700 hrs of all days

Leq (30min), dB(A)

Leq (5min), dB(A)

Average

Range

Average

Range

Average

Range

NMC01

69.3

67.8 - 70.5

69.0

61.2 - 71.8

66.6

60.6 - 71.6

NMC02

72.0

70.3 - 73.1

66.3

63.3 - 69.6

68.6

62.4 - 71.9

NMC03

78.2

77.1 - 79.5

77.9

73.3 - 82.1

73.8

65.8 - 79.7

NMC04

66.6

63.7 - 70.3

64.0

61.9 - 71.8

62.1

58.7 - 66.0

NMC05

61.8

59.2 - 64.8

59.8

56.5 - 73.7

57.9

53.6 - 62.0

Remark: Each of the daily 30 minutes sampling period include six consecutive Leq (5min) reading

 

3.7          Action and Limit Levels

 

3.7.1       The Action and Limit Levels of noise monitoring have been set in accordance with the criteria specified in the updated EM&A Manual as shown in Table 3.5 below.

 

3.7.2       Not used

 

Table 3.5 Action and Limit Levels for Construction Noise

Monitoring Station

Action Level

Limit Level (dB(A))

0700-1900 hrs on normal weekdays

0700-2300 hrs on holidays (including Sundays); and 1900-2300 hrs on all days 2

2300-0700 hrs of all days 2

NMC01

When one documented complaint is received

65 / 70 1

60 / 65 / 70 3

45 / 50 / 55 3

NMC02

75

NMC03

75

NMC04

75

NMC05

75

Remark 1: Limit level of NMC01 - Kei Shun Special School reduce to 65 dB (A) during examination periods if any.

Remark 2: Construction noise during restricted hours is under the control of Noise Control Ordinance Limit Level to be selected based on Area Sensitivity Rating.

Remark 3: Limit Level for restricted hour monitoring shall act as reference level only. Investigation would be conducted on CNP compliance if exceedance recorded during restricted hour noise monitoring period.

4              WATER QUALITY MONITORING

 

4.1          Monitoring Requirements

 

4.1.1       In accordance with the Project EM&A Manual, baseline water monitoring shall be carried out at FOUR designated monitoring stations, three days per week, for at least 4 weeks prior to the commencement of construction works. Temporal and spatial variations should be taken into account. The interval between 2 sets of monitoring should not be less than 36 hours. Replicate in-situ measures should be carried out in each sampling event. The levels of dissolved oxygen (DO), turbidity and pH shall be measured in situ while suspended solids (SS) is determined by laboratory analysis at all the designated monitoring stations.

 

4.1.2       The baseline water quality monitoring was conducted during the baseline monitoring period from 13 August 2018 to 7 September 2018 and the relevant findings are summarized in this report.

 

4.2          Monitoring Equipment

 

4.2.1       Water quality monitoring was performed using multifunctional meter and weatherproof turbidity-measuring instrument at the monitoring locations. They are capable of measuring:

ž     a dissolved oxygen level in the range of 0-20mg/L and 0-200% saturation

(Detection Limit: 0.01mg/L and 0.1%)

ž     a temperature of 0-45 degree Celsius (Detection Limit: 0.1 degree Celsius)

ž     turbidity level between 0-1000NTU (Detection Limit: 0.01NTU)

ž     salinity in the range of 0-70ppt (Detection Limit: 0.01ppt)

ž     pH value in range of 0.0-14.0 (Detection Limit: 0.01units)

 

4.2.2       Brand and model of the equipment are given in Table 4.1.

 

Table 4.1 Water Quality Monitoring Equipment

 

Equipment

Brand and model

               Series Number

Multifunctional Meter

YSI Professional Plus

14K100322

17F100236

Turbid meter

Xin Rui WGZ-3B

1403009

1309192

 

 

4.2.3       Due to low water level as mentioned in Section 6.4.3 of the EIA report, bucket sampler (Approximate 1L) will be use instead of water sampler in order to obtain surface water sample without disturb the stream sediment and collect representative results.

 

4.2.4       The calibration certificates of the water quality monitoring equipment are attached in Appendix B.

 

 

4.3          Monitoring Locations

 

4.3.1       The water quality monitoring stations for baseline water quality monitoring is presented in Table 4.2 and shown in Figures 4.1 and 4.2.

 

Table 4.2 Details of Baseline Water Quality Monitoring Stations

Inland Water

Stations

Description

Easting

Northing

Channelized nullah across the Project site

E

Upstream Control Station

841329

821753

F

Downstream Impact Station

841469

821635

Ma Yau Tong Stream

H

Upstream Control Station

843008

819880

I

Downstream Impact Station

842652

819573

 

4.4          Monitoring Parameters, Frequency and Duration

4.4.1       The monitoring parameters, frequency and duration of water quality monitoring are summarized in Table 4.3.

 

4.4.2       The levels of DO, turbidity and pH shall be measured in situ while SS is determined by laboratory analysis at all the designated monitoring stations.

 

4.4.3       In association with the water quality parameters, other relevant data shall also be recorded, such as monitoring location / position, time, water temperature, salinity, DO saturation, weather conditions, and any special phenomena underway near the monitoring station.

 

Table 4.3 Water Quality Monitoring Parameters, Frequency

Monitoring Period

Duration

Sampling Parameter

Frequency

Remarks

Baseline

Monitoring

at least 4 weeks prior to the commencement of construction works

Dissolved oxygen (DO), turbidity, suspended solids (SS) level and pH

three days per

week

Replicate in-situ measures for DO, pH and Turbidity.

4.5          Monitoring Methodology

4.5.1       Monitoring Procedure

 

(a)           The condition near the monitoring stations shall be observed and recorded on the data log sheet.

(b)           Check of sensors and electrodes with certified standard solutions before each use.

(c)           Wet bulb calibration for a DO meter should be carried out before measurement.

(d)           Sample would be taken using bucket sampler at surface level.

(e)           Transfer the sampled water carefully into cleaned water bottles (2x 500ml) provided by the laboratory at the spot after the collection of the water sample for the subsequent laboratory Suspended Solid testing.

(f)            Transfer the sampled water from the bucket sampler to the rinsed water container for in-situ measurement (In case of the in-situ measurement cannot be carried at spot due to safety and adverse weather condition, sampled water from the bucket sampler will be transfer to cleaned water bottles provided by laboratory. Then, In-situ measurement will be conducted at a safe location which sampled water inside cleaned water bottle will be transfer to the rinsed water container for in-situ measurement) In-situ measurement shall be measured in duplicate.

(g)           Parameters including Water Temperature (˘J), pH (units), Salinity (ppt), DO (mg/L), DO saturation (%) will be measured by the Multifunctional Meter and Turbidity (NTU) will be measured by turbid meter. (Water Temperature and Salinity will be measured as reference parameters)

(h)           Record the result on the data log sheet and record any special finding during / after in-situ measurement.

(i)             The water sample bottles will store in a cool box, which shall be delivered to HOKLAS laboratory (Pilot Testing Limited) for further testing to determine the level of SS.

 

4.5.2       Maintenance and Calibration

(a)           The responses of sensors and electrodes of the water quality monitoring equipment were cleaned and checked at regular intervals.

(b)           DO meter (Multifunctional Meter) and turbid meter was certified by a laboratory accredited under HOKLAS or any other international accreditation scheme, and subsequently re-calibrated at three monthly intervals.

 

4.5.3       Laboratory measurement

Analysis of suspended solid will be conducted by a HOKLAS accredited laboratory, which is Pilot Testing Limited.

 

4.6          Results and Observations

4.6.1       The baseline water quality monitoring was carried out from 13 August 2018 to 7 September 2018 and the weather was mostly sunny with traces of rainfall. During the baseline monitoring period, no construction activities were observed.

 

4.6.2       The baseline water quality monitoring results are summarized in Table 4.4 respectively. Detailed water quality monitoring results are presented in Appendix F.

 

Table 4.4 Summary of Baseline Water Quality Monitoring Results

Monitoring Station

pH

DO (mg/L)

Turbidity (NTU)

SS (mg/L)

Average

Range

Average

Range

Average

Range

Average

Range

E

7.30

6.59 - 7.95

6.48

6.02 - 6.83

24.73

7.92 - 129.90

22.55

3.25 - 175.80

F

6.94

6.28 - 8.38

6.44

5.40 - 6.82

16.46

5.46 - 78.54

9.69

1.80 - 50.95

H

7.48

6.57 - 8.51

6.23

4.83 - 7.10

184.92

7.62 - 648.48

589.76

2.95 - 5650.25

I

7.38

6.69 - 8.43

6.20

5.42 - 6.72

132.79

7.69 - 894.00

102.28

2.15 - 748.50

Remarks: The value of <1.0mg/L represents the recorded suspended solid level is under the minimum laboratory reporting limit of 1.0mg/L.

4.7          Action and Limit Levels

4.7.1       The Action and Limit Levels of water quality monitoring have been set in accordance with the derivation criteria specified in EM&A Plan as shown in Table 4.5 below.

Table 4.5 Action and Limit Levels for Water Quality Monitoring

Parameters

Action Level

Limit Level

Surface DO in mg/L

5 percentile (%-ile) of baseline data

4 mg/L or 1%-ile of baseline data

Surface SS in mg/L

95 %-ile of baseline data or 120% of control stationˇ¦s SS on the same day of measurement

25 mg/L or 99 %-ile of baseline or 130% of control stationˇ¦s SS on the same day of measurement

Surface Turbidity in NTU

95 %-ile of baseline data or 120% of control stationˇ¦s turbidity on the same day of measurement

99 %-ile of baseline or 130% of control stationˇ¦s turbidity on the same day of measurement

Surface pH

Beyond the range 6.6 to 8.4

Beyond the range of 6.5 to 8.5

 

4.7.2       Further review the baseline water quality monitoring data, the action and limit level will be derived with the following justification:

-               The turbidity and SS level recorded during baseline period at upstream monitoring stations (Monitoring Station E and H) were higher than downstream monitoring stations (Monitoring Station F and I) in general (Table 4.6, Table 4.7, Table 4.8 and Table 4.9 refers). The usage of the 120% or 130% of control stationˇ¦s (Upstream monitoring station) turbidity and SS on the same day of measurement to establish the action and limit level is not realistic in this case. As such, it is recommended that upstream monitoring station (Monitoring Station E and H) would be taken as control reference for exceedance investigation only. Action and limit level would not be established for upstream monitoring station (Monitoring Station E and H).

-               Having further reviewed the baseline water quality monitoring data, it was observed the turbidity and SS level recorded on 5 September 2018 (Maximum Turbidity and SS) at Monitoring Station F and 27 August 2018 (Maximum Turbidity and SS) at Monitoring Station I were out of the normal range as compared with other data recorded during the baseline monitoring period. As such, the SS and turbidity data recorded on those dates would take as outliers to set the Action and Limit Level in order to establish the representative action and limit levels.

-               The establishment of DO limit level using 1%-ile of baseline data was 5.5mg/L (for Monitoring Station F) and 5.4mg/L (for Monitoring Station I) which was would be stricter than using 4mg/L to set up DO limit level and would be a better limit level to safeguard the water quality monitoring.

-               After the exclusion of abnormal data, the establishment of SS limit level using 99%-ile of baseline data was 23.8 mg/L at Monitoring Station F which would be stricter than using 25mg/L as SS limit level and would be better limit level to safeguard the water quality.

-               After the exclusion of abnormal data, the establishment of SS action level using 95%-ile of baseline data at Monitoring Station I was 176.3mg/L. As such, the adoption of 25 mg/L as limit level is not realistic (Action Level > Limit Level) in this case.

-               According to Table 6.1 of EIA Report of the Project (AEIAR-195/2016) - Summary of Water Quality Objectives for Victoria Harbour WCZ, the SS annual median for inland water shall not exceed 25 mg/L due to human activity. Since the average SS level recorded for Station F on 17 August 2018 was about 25.6mg/L which was around the range stated under the WQO, the data was considered as normal.

-               According to Table 6.4 of EIA Report of the Project (AEIAR-195/2016), - Summary of Water Quality Monitoring Data for Ma Yau Tong Stream (Wet Season), the maximum Turbidity and SS level recorded was 255.5NTU and 201.5mg/L respectively. Given the data recorded for Station I on 17 August 2018 and 20 August 2018 was similar to EIA reportˇ¦s data, (i.e. 17 August 2018 - Turbidity: 197.6NTU, SS: 137.1mg/L; 20 August 2018 - Turbidity: 216.1NTU, SS: 208.5mg/L), the data was considered as normal.

 

4.7.3       The action and limit level were derived and presented in Table 4.10.

 

Table 4.6 Comparison of turbidity level at upstream and downstream monitoring station (Channelized nullah across the Project site)

Date

Monitoring Station

Comparison

Monitoring Station E (Upstream)

Monitoring Station F (Downstream)

Turbidity (NTU)

13/8/2018

8.43

5.47

Upstream>Downstream

15/8/2018

21.71

9.72

Upstream>Downstream

17/8/2018

129.90

34.79

Upstream>Downstream

20/8/2018

14.00

8.87

Upstream>Downstream

22/8/2018

8.84

7.09

Upstream>Downstream

24/8/2018

15.87

5.46

Upstream>Downstream

27/8/2018

20.00

6.78

Upstream>Downstream

29/8/2018

18.26

12.19

Upstream>Downstream

31/8/2018

7.99

14.07

Downstream>Upstream

3/9/2018

7.92

6.85

Upstream>Downstream

5/9/2018

34.46

78.54

Downstream>Upstream

7/9/2018

9.39

7.73

Upstream>Downstream

 

Table 4.7 Comparison of SS level at upstream and downstream monitoring station (Channelized nullah across the Project site)

Date

Monitoring Station

Comparison

Monitoring Station E (Upstream)

Monitoring Station F (Downstream)

SS (mg/L)

13/8/2018

6.55

3.65

Upstream>Downstream

15/8/2018

5.70

3.00

Upstream>Downstream

17/8/2018

175.80

25.55

Upstream>Downstream

20/8/2018

8.35

6.25

Upstream>Downstream

22/8/2018

5.65

2.85

Upstream>Downstream

24/8/2018

10.30

2.95

Upstream>Downstream

27/8/2018

5.55

5.35

Upstream>Downstream

29/8/2018

3.25

3.60

Downstream>Upstream

31/8/2018

4.30

8.45

Downstream>Upstream

3/9/2018

8.95

1.80

Upstream>Downstream

5/9/2018

31.85

50.95

Downstream>Upstream

7/9/2018

4.30

1.85

Upstream>Downstream

 

Table 4.8 Comparison of turbidity level at upstream and downstream monitoring station (Ma Yau Tong Stream)

Date

Monitoring Station

Comparison

Monitoring Station H (Upstream)

Monitoring Station I (Downstream)

Turbidity (NTU)

13/8/2018

193.43

64.32

Upstream>Downstream

15/8/2018

61.46

26.65

Upstream>Downstream

17/8/2018

423.80

197.63

Upstream>Downstream

20/8/2018

392.95

216.08

Upstream>Downstream

22/8/2018

53.26

49.15

Upstream>Downstream

24/8/2018

310.00

82.27

Upstream>Downstream

27/8/2018

648.48

894.00

Downstream>Upstream

29/8/2018

69.32

13.57

Upstream>Downstream

31/8/2018

23.66

13.23

Upstream>Downstream

3/9/2018

21.65

17.99

Upstream>Downstream

5/9/2018

13.40

10.93

Upstream>Downstream

7/9/2018

7.62

7.69

Downstream>Upstream

 

Table 4.9 Comparison of SS level at upstream and downstream monitoring station (Ma Yau Tong Stream)

Date

Monitoring Station

Comparison

Monitoring Station H (Upstream)

Monitoring Station I (Downstream)

SS (mg/L)

13/8/2018

120.2

39.6

Upstream>Downstream

15/8/2018

24.1

11.5

Upstream>Downstream

17/8/2018

459.6

137.1

Upstream>Downstream

20/8/2018

439.1

208.5

Upstream>Downstream

22/8/2018

23.0

10.8

Upstream>Downstream

24/8/2018

254.5

44.0

Upstream>Downstream

27/8/2018

5650.3

748.5

Upstream>Downstream

29/8/2018

59.7

6.5

Upstream>Downstream

31/8/2018

23.2

9.6

Upstream>Downstream

3/9/2018

17.4

6.9

Upstream>Downstream

5/9/2018

3.0

2.4

Upstream>Downstream

7/9/2018

3.4

2.2

Upstream>Downstream

Table 4.10 Derived Action and Limit levels

Monitoring Station

Surface pH

Surface DO (mg/L)

Surface Turbidity (NTU)

Surface SS (mg/L)

Action Level

Limit Level

Action Level

Limit Level

Action Level

Limit Level

Action Level

Limit Level

E

-

-

-

-

-

-

-

-

F

Beyond the range 6.6-8.4

Beyond the range 6.5-8.5

5.8

5.5

24.4

32.7

17.0

23.8

H

-

-

-

-

-

-

-

-

I

Beyond the range 6.6-8.4

Beyond the range 6.5-8.5

5.5

5.4

206.9

214.2

172.8

201.4

 

*Remarks:

The value of 1.0mg/L was taken as the value for measurement with suspended solid level of <1.0mg/L for Action and Limit level calculation.

It is recommended that upstream monitoring station (monitoring station E and H) would be taken as control reference for exceedance investigation only. Action and limit level would not be established using the baseline data.

 

 

5              Revision for inclusion into EM&A Manual

 

5.1.1       With respect to fine adjustment of monitoring locations were proposed in the baseline monitoring report, the fine adjusted air and noise monitoring locations are recommended in the EM&A manual. It is also recommended that the air and noise monitoring station condition should be regularly reviewed and fine adjustment or relocation may be needed in order to obtain respective impact monitoring results. The fine adjustment or relocation of monitoring location shall be addressed in the updated EM&A manual during impact monitoring.

 

6              Comment and Conclusions

 

Comment

 

Water Quality of Seasonal Changes

6.1.1       The nature of monitoring streams is for rainwater drainage. The catchment areas of those streams are widely ranged and collected the rainwater and nature surface runoff across the stream catchment area at Clear Water Bay Road and Ma Yau Tong Stream.

6.1.2       For impact water quality monitoring during wet season, it is anticipated the water quality monitoring results may be similar to the baseline condition with a wide range of recorded Turbidity and SS. As such, it is recommended that the water quality monitoring shall act as an alarm system to review the site condition. Review of site drainage and inspection along site boundary shall be conducted by Contractor / RSS / ET to ensure no surface runoff or seepage into the monitoring stream and cause contamination. Monitoring condition during adverse weather shall also be recorded to avoid false alarm.

6.1.3       For impact water quality monitoring during dry season, the water quality monitoring may not be feasible due to the extremely shallow of water at the monitoring station. In case the situation was not feasible for monitoring due to insufficient water flow, it is recommended that inspection around the monitoring station to be conducted by ET to record the stream condition.

 

Air Quality of Seasonal Changes

6.1.4       Baseline air quality monitoring was conducted during typical Hong Kong wet season. The baseline data collected therefore represent the baseline air quality of the wet season immediately prior to commencement of the Project. It is therefore recommended that the interpretation of the air quality monitoring data should take into account the influence of the seasonal changes, and the baseline conditions should be regularly reviewed.

 

Other noise sources

6.1.5       Baseline noise monitoring was conducted prior to the construction works start. During the baseline monitoring period, no construction activities were observed. The major noise source was traffic noise around the monitoring stations (especially Clear Water Bay Road near NMC03). It is possible that other noise sources would be identified during the impact monitoring period such as other development project, road works or public activities around the monitoring locations. It is recommended that the noise monitoring station condition should be regularly reviewed and fine adjustment or relocation may be needed in order to obtain respective impact monitoring results.

 

6.1.6       Not used

 

Conclusion

 

6.1.7       In accordance with the Project EM&A Manual and EP, baseline monitoring has been undertaken prior to commencement of the construction works of the Contract for the following baseline monitoring components: Air Quality; Noise and Water Quality.

 

6.1.8       As highlighted under Tables 2.2 and 3.2, several fine adjustments of locations were proposed for baseline monitoring. Nevertheless, given the fine adjusted location with similar pollution sources and prevailing meteorological condition to the original locations recommended in the EM&A manual, it is considered to be representative for the air and noise sensitive receiver identified in EIA manual.

 

6.1.9       The baseline air quality monitoring was conducted at eight (8) monitoring locations from 13 to 29 August 2018. Overall, the baseline air quality monitoring results are considered representative to the ambient air quality conditions of the respective sensitive receivers. The Action and Limit Levels for air quality (for 1-hour TSP levels) were established based on the baseline monitoring results.

 

6.1.10    Baseline noise monitoring was conducted at five (5) designated monitoring stations from 13 August 2018 to 2 September 2018. The major noise sources identified at the monitoring station are the noise from traffic noise. The baseline monitoring results are considered representative of the ambient noise level.

 

6.1.11    Baseline water quality monitoring was conducted at four (4) monitoring stations from 13 August 2018 to 7 September 2018. No observable pollution source was recorded at the monitoring stations and the baseline monitoring results are thus considered representative of the ambient water quality levels. Action and Limit Levels were established for DO, SS and turbidity based on the baseline monitoring results.